Concrete Placement
Three issues are critical to the placement of concrete under water or slurry:
- A delivery method must be used that keeps the concrete separated from the water or slurry and prevents intermixing.
- The concrete must maintain a high slump to completely fill the shaft and flow easily around the reinforcing steel.
- The top of the shaft must be thoroughly flushed at completion of the pour.
The Delivery – Concrete placed under water or slurry must be placed through a closed, sealed tremie or with a pump. At the start of the pour, some means must be provided to separate the concrete from the water or slurry. Most commonly, the open tremie is inserted to the bottom of the excavation and allowed to fill with water or slurry. A foam rubber plug, usually called a “pig,” is placed in the top of the tremie pipe before the hopper is filled with concrete. As concrete enters the tremie pipe, the pig slides down, separating the concrete from the water or slurry. Once the tremie pipe and hopper are full of concrete, lifting the tremie pipe slightly allows the pig to be expelled, and concrete begins flowing into the shaft. Concrete with the correct slump often will flow up the sides of the tremie a considerable distance (10-20 ft.) while the hopper is recharged with concrete as needed. Once the flow slows or stops, the tremie is lifted to restart the flow. It is critically important that the trremie remain well embedded in the concrete. Five feet of embedment should be maintained as a minimum at all times. This can be checked using a weighted tape to determine the level of concrete within the shaft, and then calculating tremie embedment based on the measured length of the tremie. Failure to maintain tremie embedment will trap the soil cuttings, sediment and washed-out concrete in the shaft. In a correct pour, these materials remain on top of the concrete, and are flushed off at the top of the shaft at the end of the pour.
Pumped concrete is placed in a similar manner. The concrete and water must be prevented from mixing at the start of the pour, and a foam rubber plug often is used in the pump line as a separator. Additionally, embedment of the pump line into the concrete is critical throughout the pour.
Concrete Slump – Using a high-slump concrete and maintaining slump during the pour are keys to a quality drilled shaft. For underwater placement of drilled shafts, the slump should be too high rather than too low. Low-slump concrete will not flow out through the tremie and around reinforcing steel in the manner necessary to achieve a quality shaft. Many exposed shafts poured with low-slump concrete have honeycombing outside the reinforcing steel cage, or, in some cases, they have no concrete at all. Drilled shaft concrete should have a slump of 8 inches, with a maximum of 9 inches allowed.
Retention of slump throughout the concrete pour also is important. Adequate retarder must be included in the concrete to retain workable slump throughout the duration of the pour. Inadequate retardation can cause the upper portion of the concrete to stiffen as it begins to set during the pour. If this occurs, the tremie must be raised very near the surface (or out) of the concrete to restore flow. When this happens, the concrete actually flows up alongside the tremie and over the top of the stiffened concrete, including cuttings, sediment and diluted concrete. This may happen several times during a lengthy pour if slump is not maintained. Concrete used for underwater pours should maintain a 4-inch slump for the duration of concrete placement, including extraction of casing if it used.
Completing the Pour – During an underwater pour, cuttings, sediments and diluted concrete are carried to the top of the concrete column as it is being placed. As the pour is completed, all loose material and contaminated concrete should be flushed off the top of the shaft. In some cases a cubic yard or more of concrete will be wasted to assure that all contaminated material is removed. The top of the shaft should be strongly flushed while concrete is being placed through the tremie or pump at the same rate as the rest of the pour. Attempting to dip or shovel this material off the shaft often leaves behind inclusions and low-quality concrete.
ND
This article is provided through the courtesy of the Texas Department of Transportation.