Backreaming through Rock
January 3, 2012
Taking on a challenge is nothing out of the ordinary
for the experienced trenchless installation experts at Midwest Mole. Since its
founding in 1982, the Indianapolis-based contracting firm has earned a reputation
for installation innovation, overcoming obstacles, and defying the odds. So,
these trenchless pros didn’t hesitate to take on another challenge despite the
recognition that they would likely encounter a few unknown and unexpected
twists and turns along the way.
Midwest Mole was hired by general contractor Dudley Construction on behalf of
project owner Northern Kentucky Sanitation District No. 1 (SD1). SD1 is
responsible for the collection and treatment of Northern
Kentucky’s wastewater, as well as regional storm water management,
and is the second-largest public sewer utility in the state. The district’s
service area covers approximately 220 square miles in three Northern
Kentucky counties, serving more than 30 municipalities and several
unincorporated areas. SD1 maintains more than 1,600 miles of sanitary sewer
line, more than 140 wastewater pumping stations, several treatment plants, and
approximately 17,800 storm sewer structures.
This project, located just outside of Florence, Ky., was to install a 506-foot
section of 18-inch DR11 HDPE material that would eliminate a pump station, and
convert the existing sewer from a forced main to gravity flow. It was to be
installed at 1.3-percent grade using auger boring as the installation method.
The greatest challenge, however, was neither the grade nor the material, or
even restricted access to the site – which would necessitate traversing over
hilly, heavily wooded terrain – but as often is the case, it would be ground
conditions posing the bigger concern. After reviewing the plan, however, David
Howell, a project manager for Midwest Mole, had an idea for an alternative
approach.
“This was in a residential area with a lot of trees, on a hill, and with very
limited access,” Howell relates. “It was was solid rock. SD1 had designed it to
basically be bored through the hill with the auger-boring method. We had used
the Vermeer AXIS guided-boring system on a project before, and thought it might
be a good fit here. Our only real concern was backreaming through rock.”
How the System Works
The AXIS system consists of a vacuum power unit, vacuum tank and the rack power
unit, along with drill casing and the drill head. Located outside the launch
pit is a high-performance liquid ring vacuum power unit that removes excavated
material from the bore. Upon reaching the launch pit, the excavated material
transitions from the drill casing to a 6-inch-diameter hose that runs up the
launch pit to the vacuum tank.
Outside the pit is a self-contained power unit that features a 140-HP diesel
engine, and hydraulic pumps that connect to a rack (located in the launch pit)
that powers rotation, thrust and pullback functions of the drill head and
casing.
The operator console is designed to centralize control of multiple components
into an easy-to-use interface, and consists of the target display monitor,
parameter display, drill-head steering control, thrust/pullback con-trol,
rotation control and vacuum controls. Drill casing segments, measuring 6.5 feet
long, are placed in the rack carriage, and feature a laser sight channel and a
vacuum channel for removing excavated material.
The guidance system includes a laser that determines the line and grade of the
bore, enabling on-grade accuracy throughout the bore process. The drillhead
uses a flat-face cutter, that when combined with the laser-guidance system, is
capable of completing bores with precise tolerances of on-grade accuracy. In
standing ground, it can be retracted in mid-installation, allowing the
contractor to change the cutter bit to adapt to changing soil conditions.
Enhanced Efficiency
The rock was composed of layered shale with veins of limestone formations
ranging from 1 inch to 5 inches thick, and measuring upwards of 12,000 psi. The
overhead power line and an existing pump station located within close proximity
of where the launch pit area would need to be situated also were factors.
However, after verifying the location of the sewer lines currently running in
and out of the pump station, and sizing up the final measurements for
positioning the various components of the AXIS system, Howell was confident
that this laser-guided boring method was, indeed, the best approach, and
officials with SD1 concurred.
“While we agreed that it certainly would have been possible to complete the job
using auger boring, we were able to identify several advantages that favored
the AXIS system, and presented these findings to officials at our longtime
customer, SD1. They weren’t all that familiar with this method, but we had
worked with them on several prior projects, and were delighted they trusted our
recommendation and gave us the green light.”
Howell cited three important factors that helped tip the scale in favor of the
AXIS system, beginning with the rock. The inconsistency of the formation and
the variation in limestone and shale layers make it more difficult to maintain
an accurate line and grade using auger boring. According to Howell, maintaining
a precise grade – often less than 1 percent – is a major advantage for AXIS, as
the laser-guided system allows the operator to continuously monitor the boring
process and make adjustments when changes in rock density and hardness alter
the path of the drillhead, albeit ever so slightly.
Another important advantage for the AXIS system given the rocky Northern
Kentucky terrain, coupled with the smaller-diameter material that was to be
installed for the Florence project, is the ability to complete it in one
pass.
“Auger boring would have necessitated a two-pass approach,” Howell explains.
“The casing pipe would have to be installed first, followed by the new carrier
pipe threaded inside that. And likely this approach also would have required
that we grout the material in place. Not so using the AXIS system, however, as
the carrier pipe could be installed directly in the bore minus the steel
casing. So, in essence, we eliminated a step, and that equates to less time and
reduced expense.”
Midwest Mole used a 13-inch tri-cone bit for the pilot bore, and achieved an
average production rate of 14 feet per hour through this complex compilation of
rock formations. With the HDPE pipe fused and ready on the receiving end, it
was time to face the unknown and begin the backreaming phase of the project.
The one unknown, however, was whether the AXIS system would be able to backream
through this difficult formation of limestone, shale and high-density rock,
having only pulled product back through the bore on previous installations.
Howell’s crew selected a 191⁄4-inch tri-cone cutter head for navigating the
506-foot bore with roller cones – a tooling configuration considered to be
effective for removing rock, and best positioning the reamer during pullback.
“This was the first time the AXIS system had been used to ream rock, so there
was obviously some trial and error involved at first,” Howell says. “We made
some adjustments along the way to get the cutter spacing set with the correct
over-cut to allow the reamer to work most efficiently. We had a pulling head
attached to the back side of the reamer on a swivel, which helps to clear the
bore, so we were pulling the product pipe back in as the hole was reamed. We
used the standard Vermeer reamer design custom-built with roller-cone cutting
heads.”
Calming of the Nerves
Howell admitted there were some nervous moments prior to pulling back. “We knew
that we had thought out the project as thoroughly as possible, but there still
were some tense nerves as we approached backreaming time,” Howell notes.
“Vermeer was there to support us, and yes, there was nervousness doing
something for the first time, but, all in all, things went very well. We had to
make some adjustments, but at the end of the day, it actually reamed the rock
quite well, and we were very pleased with it. We averaged about eight feet an
hour on the
backream.”
Howell and crew are looking forward to the next chance to break ground and make
history on another trenchless installation project. Until then, however, the
capable pros at Midwest Mole are content having accomplished another historic
bore successfully, but more so, having continued to solidify a customer
relationship.
“We are proud of the many installations we’ve completed successfully,” Howell
says. “But we’re even more proud of the trust and credibility we’ve been able
to establish with customers like SD1. We went a bit out on a limb with this one,
and fortunately, all worked well as they [SD1] are quite happy with the
results.” ND
|